6 hrs, 11 rivets
Many partially finished tasks have piled up, all pending completion of some other task. Getting the FAB, cowling, and cowling fastener system done breaks the log jam. So now it's time to knock out the thousand little tasks needed to complete FWF and engine monitoring systems.
Finish painting and rivet lower cowling bracket parts.
Install carb temp probe.
Install carburetor.
Install FAB.
Cut to length and install carb heat cable.
Change out oil pressure restrictor and install oil pressure cable.
Attach ground strap to engine.
Fabricate clips for winscreen and drill to forward top skin.